Viewing this weeks tasks in Microsoft Project

I received this question from a customer:

Question:

I have a project plan which shows all the key tasks and as part of a weekly project meeting I’d like to be able to apply some filter that would only show those tasks that should have been completed that particular week. Is there any functionality such as that within MSP that I can use?

 

Answer: